Adams St Resurfacing

Project Description: Mill and resurface Adams St. between Middle Turnpike West and Tolland Turnpike.  Includes installation of new sidewalks on west side of Adams St. between traffic signal at Manchester Materials driveway and Tolland Turnpike.
Funding Source: Local Transportation Capital Improvement Program (100% State funded)
Construction Cost: $1,075,095.00
Contractor: The Nunes Companies
Start Construction: April 2020
End Construction: July 2020