Project Description: Construction of a ten-stall parking lot and 500' of bituminous sidewalk at 363 Broad Street to provide pedestrian connection to Center Springs Park.
Funding Source: Broad Street Redevelopment (Bond Referendum)
Construction Cost: $250,000. (Estimated)
Contractor: To be bid
Start Construction: May 2017
End Construction: July 2017