Manchester, Connecticut

2020 Paving Contract 3

Project Description: Mill and overlay surface course of pavement at the following locations:
-Vernon Street (Middle Turnpike East to Lydall St)
-Adams Street (Center St to Middle Turnpike West)
-Middle Turnpike West (Adams St to Green Manor Blvd)
-Porter Street
-Mather Street
-Cambridge Street
-Sheldon Road
Funding Source: 2019 Public Works Bond Referendum
Construction Cost: $ 1,700,000.00
Contractor: American Industries Inc.
Start Construction: July 2020
End Construction: September 2020